Description
The i2b2 1.7.05 release included a change to the PM cell that fixed a problem where the PM cell was not always sending the correct cell information will multiple projects and cells were defined (CORE-156).
Although the fix made in 1.7.05 did correct the issue for i2b2 users it has caused a problem for SHRINE users in that they are not able to run queries if they are using SHRINE version 1.18 (or earlier) and i2b2 version 1.7.05 in their local instance.
Ultimately a fix needs to be made to the SHRINE software by the SHRINE team. In the meantime, the i2b2 team will address this issue in the i2b2 software to try and prevent any backwards compatibility problems that may occur.
Although the fix made in 1.7.05 did correct the issue for i2b2 users it has caused a problem for SHRINE users in that they are not able to run queries if they are using SHRINE version 1.18 (or earlier) and i2b2 version 1.7.05 in their local instance.
Ultimately a fix needs to be made to the SHRINE software by the SHRINE team. In the meantime, the i2b2 team will address this issue in the i2b2 software to try and prevent any backwards compatibility problems that may occur.
Attachments
Issue Links
- related to
-
CORE-156 PM may not send the correct cell information when multiple projects and cells defined